Corridor description
The total length of North Sea – Rhine – Mediterranean Corridor (NSRM) is approximately 12 000 km long, including the Connecting Europe Facility 2 (CEF 2) extension. It crosses 8 countries: the Netherlands, Belgium, France, Luxembourg, Ireland, Germany, Switzerland, and Italy.
The NSRM constitutes one of the busiest freight routes in Europe, connecting the North Sea ports of Rotterdam and Antwerp to the Mediterranean basin in Genoa, via Switzerland and some of the major economic centres in the Rhine-Ruhr and the Rhine-Main-Neckar regions and the agglomeration of Milan in northern Italy. It also provides connections to several east-west axes.
ERTMS deployment on the corridor
At the end of 2024, ETCS was operational on 21% (2 600 km) of NSRM, 20% more (2 400) were under construction, while GSM-R was operational on 93% of the corridor. According to the TEN-T Guidelines, 48% of the Core network of the NSRM corridor is expected to be equipped by 2030.
- In Ireland, there are plans to deploy ETCS on the existing lines between 2025 and 2040, the lines planned by 2027 are already under construction. There is also a new line not included in the Irish ETCS deployment plan.
- In The Netherlands, ETCS is already in operation in several lines of NSRM. According to the Dutch plans, only Barendrecht – Essen, Roosendal – Vlissingen and Vlissingen port are planned to be equipped with ETCS by 2035, but the majority of Dutch lines in NSB are planned by 2050. There are two lines not included in the Dutch ETCS deployment plans.
- According to the German plans, slightly more than 50% of NSRM network is scheduled to be commissioned by 2030, while the rest 50% of the network is planned by 2043.
- According to Belgium national plan, ETCS is already in operation for most of the NSRM lines. The commissioning of ETCS on the rest of NSRM sections is planned by 2025, with the exception of the line Border FR/BE (Wannehein) - Halle which is planned by 2030. There is also a new line not included in Belgium deployment national plan.
- In France, ETCS is already in operation on some NSRM lines. Thera are plans for commissioning of ETCS on the rest of NSRM sections until 2044, but slightly more than 50% of the NSRM corridor lines are not included in France's ETCS deployment plan.
- Switzerland and Luxembourg have his entire network regarding to NSRM corridor with ETCS in operation.
- In Italy, ETCS is already in operation in a few lines of NSRM corridor. According to the Italian plans, ETCS deployment on lines of the NSRM corridor is planned between 2025 and 2037. The existing lines Seregno – Novara and Novara – Novara Interporto are not included in the Italian ETCS deployment plan.