Corridor description
The total length of the Western Balkans-Eastern Mediterranean (WBEM) European Transport Corridor (ETC) is 6 200 Km. It crosses 12 countries: Austria, Italy, Slovenia, Hungary, Croatia, Bosnia and Herzegovina, Serbia, Montenegro, Albania, Bulgaria, North Macedonia, Greece.
Crossing the Balkan countries, the corridor provides a great connection point to the rest of the European continent by finding its roots in Austria while extending until important port areas (Thessaloniki, Athens, Rijeka, Trieste, Durrës).
ERTMS deployment on the corridor
Overall, ETCS is in operation on 600 km (10%) of the WBEM corridor, under construction on 1 400 km (22%), while GSM-R is operational on 31% of the corridor. 39% of the WBEM Core TEN-T Network in EU member states is expected to be completed by 2030.
The deployment status per Member State where the WBEM corridor runs is as follows:
- In Austria, a limited number of lines are scheduled for ETCS implementation between 2025 and 2028. The majority of the WBEM corridor lines, however, are planned for ETCS deployment between 2030 and 2037.
- In Hungary, ETCS installation is already under construction and is expected to be completed across the WBEM ETC network by 2026.
- Approximately half of the lines in the WBEM corridor, ETCS is installed but not in service in Slovenia. Zidani Most – Dobova (Border SI/HR) section is the only line currently operating with ETCS. The existing network belonging to WBEM corridor are scheduled to be commissioned by 2030, with the exception of the line Ljubljana - Jesenice (Border SI/AT) which is expected to be put in operation by 2040. There is a new high-speed line not included in the Slovenian ETCS deployment plan.
- In Croatia, the sections Novska - Okučani and Vinkovci - Tovarnik are already in operation with ETCS. The Vinkovci–Borovo Naselje section is under construction with ETCS and was planned for completion by 2024, according to the 2024 Croatian NIP. However, no confirmation has been received regarding its entry into service. The remaining sections of the Croatian WBEM corridor network are scheduled for deployment between 2033 and 2040, with most expected to be operational by 2040.
- According to Serbian Network Statement, ETCS is already in operation on the line Belgrade - Novi Sad. There are a few lines already under construction planned by 2024, according to news, but no information has been received that they have already been put into service. There are no ETCS deployment plans for most of Serbia lines within WBEM corridor.
- According to Italian national plan, the few lines within the WBEM corridor are scheduled to be equipped with ETCS between 2028 and 2029.
- In Bosnia and Herzegovina and Montenegro there are no ETCS deployment plans for the WBEM corridor network.
- In Bulgaria, nearly half of the WBEM network is already operational with ETCS. The Dragoman–Sofia line is under construction and scheduled for completion by 2028. The Svilengrad – Svilengrad east line is planned by 2030. The remaining half of the WBEM corridor network is not included in Bulgaria’s ETCS deployment plan.
- In Albania and North Macedonia there are no ETCS deployment plans for the WBEM corridor network.